Preparation of completion Reports
Monday, September 22nd, 2008After completing the electrical installation works of a new HV/EHV installation or making additions to an existing HV/EHV installation, the electrical contractor who carried out the installation works shall conduct the necessary pre-commission checks and tests and prepare the completion report in the prescribed format. The completion report shall be signed by the electrical contractor and the owner of the installation and submitted to the Electrical Inspectorate and the supply authority. A model form ofthe completion report is given at the end of this chapter. The completion report shall necessarily contain the following details 1. Full name plate details of all electrical machines and equipments covered in the completion report. 2. Test results of main equipments and switch boards. 3. read more